Major progress onsite at the ESR Australia Coolaroo Industry Park project with the Warehouse 1 structure completed and office slabs being poured.
The Warehouse 3 structure is underway and bulk earthworks are progressing at Warehouse 2.
The site civil stormwater works are also underway.
A great effort by everyone who is involved with the delivery of this project.
This project sees Vaughan building three free-standing warehouses- Warehouse 1: 9,580m², Warehouse 2: 17,762m² and Warehouse 3: 17,890m².
Warehouse 2 includes two tenancies: Warehouse 2A with 11,494m² and Warehouse 2B with 6,268m². Warehouse 3 also has two tenancies: Warehouse 3A with 10,306m² and Warehouse 3B with 7,584m².
The buildings will have flexible loading with recessed docks and on-grade loading. Warehouse 2 and Warehouse 3 will have 36-metre-wide super awnings and Warehouse 1 will have a 15-metre-wide cantilevered canopy.
External areas to be delivered include 17,580m² of heavy-duty concrete and 9,680m² of car parking area.